SANITATION DEPARTMENT
PROGRESS REPORT
September 8th-12th 2008
Prepared by : Quiania Williams, Vic Jordan
Specific Weekly Activities:
Monday 9/8/2008
Ran the regular Lake View trash route
Picked up boxes from local merchants ..
Total tonnage & cost to landfill:36.92tn,$1033.76cost
Tuesday 9/9/2008
Ran the regular trash route @ 4:00 a.m.
Picked up boxes from local merchants…
Fred's, Jungel, Fred Dollar Store,
Unit# 27 broke down on way to landfill (temporary out of service)
Total tonnage & cost to landfill;62.20tn, $1741.60cost
Wednesday 9/10/2008
Ran regular trash routes
Continued to pick up boxes from local merchants
Delivered several trash carts to new residents..
326 Desoto
503 Arkansas
505 Arkansas
Picked up list from Water Dept of carts that need to be picked up
Mechanic took hydraulic pump off unit #21 for repair
Total tonnage and cost to landfill:39.64tn, $1109.92
Thursday 9/11/2008
Ran regular trash route
Victor picked up cylinder for unit #30 (Century Hydraulic in West Memphis,Ark)
Continued to pick up missed trash/deliver carts to new residents
Total tonnage and cost delivered to landfill:39.14tn,$1095.92cost
Friday 9/12/2008
Continued to run the regular routes @ 4:00 a.m.
Picked up boxes from merchants
Tyrone Collins removed remains of burnt houses on Hernando Street(2 houses)
No visible addresses were present (200&300blk)
Total tonnage and cost delivered to landfill:34.85tn,$975.80cost
Total tonnage and cost delivered to landfill week of 9/8/2008 thru 9/12/2008=212.75tn, $5957.00cost
Future Weekly Activities:
Follow up on demolition projects
Continue working with Code Enforcement and other Depts.
Continue with picking up trash on daily basis
Follow Up Activities:
Electronic Waste Arrangements
Staff Concerns:
Mark Smith out on sick leave until further notice
John Smith out until further notice
3 drivers were suspended this week for not following procedures