East Water Weekly Report 05/26/09
Weekly Department Report
Date: 05-22-09
Prepared by: Terry McGinister
Specific Weekly Activities 5/15/09 - 5/21/09
Checked lift stations
Unstopped storm drains on Pecan and Perry Street
Repaired main back wash valve at the plant
Repaired air compressor
Cut grass around tanks and lift stations
Repaired pump #2 at lift station #1
Unstopped sewer on Walnut and surrounding areas
Unloaded chemical truck at the plant
Filled in pot holes with cold mix
Future Weekly Activities
Replace suction valve and pump at lift station #3
Follow up Activities
Finish putting riprap on levees at the ponds, finish installing by pass hook up at the remaining lift station and rehab lift station #9
Staff Concerns/Issues
Scheduling classes for all employees to attend to have enough hours to renew their licenses