Department: 92 PLAZA 72390 Date June 01, 2009 Prepared by KEN FRATESI (05/29/09) WEEK OF _05/22/09—05/28/09 ELEVENTH AND SOUTH ASHLAR REPAIR SEWER 614 WEST GARLAND MTC METER SET COMPLETED NEW SET 834 FAIRWOOD 854 968 HWY 49 MTC SERVICE BACKFILL PREVIOUS REPAIRS CLEAN SEWERS: 200 BLK ASHLAR, CUT GRASS READ METERS Future Weekly Activities: CHECK PROBLEM SEWERS Follow Up Activities: HAVE ISSUED PROCEED TO WORK ORDER ON BOTH PUMP STATION REHABS. Staff Concerns/Issues: |