Specific Weekly Activities 8/14/09 -  8/20/09
 
Serviced company trucks
Checked lift stations
Cut grass at lift stations, tanks and wells
Completed weekly report
Daily locates and service calls
Completed water project at Waverly Woods
Flushed fire hydrants on Oak Forest
Unstopped sewer  on Valley Drive, Pecan and Walnut Street
Fixed water main on Locust, Moore and Cherry Street
Employees attended monthly city safety meeting
 
Future Weekly Activities
Replace suction valve and pump at lift station #3
 
 
Follow up Activities
Finish putting rip rap on levees at the ponds, finish installing by pass hook up at the remaining lift stations
 
 
Staff Concern/Issues
Scheduling classes for all employees  to attend to have enough hours to renew their licenses