East Water Weekly Report 9/28/09
Weekly Department Report
Date: 9/24/09
Prepared by: Terry McGinister
Specific Weekly Activities 9/18/09 - 9/24/09
Monthly cut offs
Checked lift stations
Unstopped sewer at Valley Drive, Pecan, and Walnut Street
Changed out chlorine cylinders at booster stations ( Industrial Park and Highway 20)
Changed out chemicals at the plant
Cut grass at the plant and around fire hydrants
Replaced 2" inch water main at Violet Circle
Repaired 4" inch water main at Beech Street
All employees turned in drivers record from the Revenue Department
Worked on hydromatic booster station
Future Weekly Activities
Replace suction valve and pump at lift station #3
Follow up Activities
Finish putting rip rap on levees at the ponds, finish installing by pass hook up at the remaining lift stations
Staff Concerns/Issues
Scheduling classes for all employees to attend to have enough hours to renew their licenses