East Water Weekly Report
Weekly Department Report
Date: 12/30/10
Prepared by: Terry McGinister
Specific Weekly Activities 12/23/10 - 12/29/10
Daily Arkansas Once call locates
Daily service calls
Cleaned up water plant and chemical building
Checked sewer lift stations
Unstopped sewer on McDonough and Pecan Street
Worked on pump #2 at lift station #4
Weekly report to the office
Holiday Weekend
Future Weekly Activities
Finish repairs on pump at lift station #1
Follow up Activities
Finish putting rip rap on levees at the sewer ponds and finish installing by pass hook ups at sewer stations #2, #4, and #6
Staff Concerns/Issues
Scheduling classes for all employee license renewal