East Water Weekly Report
Weekly Department Report
Date: 12/08/10
Prepared by: Terry McGinister
Specific Weekly Activities 12/03/10 - 12/07/10
Daily Arkansas One call locates
Daily service calls
Monthly meter readings
Checked sewer lift stations
Uncovered sewer man hole at Military Road
Replaced lights at lift station #2, and #3
Changed out chemicals at the water plant
Repaired cabinets in the lab
Completed weekly reports
Future Weekly Activities
Finish repairs on pump at sewer lift station #1
Follow up Activities
Finish putting rip rap on levees at the sewer ponds and finish installing by pass hook ups at sewer lift stations #2, #4 and #6
Staff Concerns/Issues
Scheduling classes for all employee license renewal
No comments: